[wsf-c-dev] 2007 Q1 Release Planning

Samisa Abeysinghe samisa at wso2.com
Sun Dec 31 22:43:21 PST 2006


I have done some planning around the 2:1 release model.

Please follow the following links:
WSF/PHP
http://www.wso2.org/wiki/display/wsfphp/Release+Plan+2007+Q1

WSF/C
http://www.wso2.org/wiki/display/wsfc/Release+Plan+2007+Q1

Project Plan
http://tools.wso2.net/~samisa/C-Team-Projects.planner

Please have a look at the Gantt chart of the project planner to get a 
better understanding of how you have been allocated.
For most of the tasks, I have already created Jiras along with sub 
tasks. If you feel more Jiras are requires, or more sub tasks are 
required, please create them and update the wiki pages.
Also if you have any concerns on any allocations or timing/scheduling, 
this is the time to raise them.

Please note that, I have not allocated many of you for March, which is 
the release month. Task allocation for the release moth would be done 
towards the end of Jan or beginning of Feb.

Thanks,
Samisa...